Comfort and Convenience from Top to Bottom
One trade is responsible for installing the elevators and escalators. Spanning seven levels, the main terminal building is quite tall. To ensure…
Precise Preparations and Exacting Work
Materials were temporarily stored just west of the main terminal building. The required rotating tower cranes were also installed there. The auxiliary…
During times of peak activity, up to 300 truckloads of earth were excavated each day.
Lots to Discover
This interactive informational graphic provides an overview of the area, showing what was…
It Gets Wet
During the special underwater engineering phase, the pit’s depth is increased from eight to 11 meters. This is necessary in order to build Terminal 3 so that departing travelers can…
From Check-In to Shopping and Dining
The heart of Terminal 3 beats where passengers start their trips and are welcomed back by their loved ones: in the main building. It has three zones:
A…
The First Stone in the Wall
The cornerstone ceremony took place at the Terminal 3 construction site on April 29, 2019 with about 700 invited guests. The stone contains a time capsule that was…